A. Purpose.
2. Responsibility for
Capital Improvement Projects.
All Capital Improvement Projects for the university
are under the direction of the Office of the Vice Chancellor for Business
Affairs. Specifically, the individual designated to be the primary contact
is the Capital Projects Coordinator, who is presently the Assistant Vice
Chancellor for Business Affairs-Facilities.
3. Working Drawings and
Bid Document Phase.
The next phase (working drawings and bid documents)
is a largely technical phase and will be handled by the Capital Projects
Coordinator and the designer up through the bidding process. Once the bidding
has taken place, approximately a month is required to have the contractor(s)
legally under contract by execution of the proper documents. At this point,
the Capital Projects Coordinator will issue a "Notice to Proceed," in conjunction
with the Office of State Construction. The construction time frame begins
with the "Notice to Proceed."
4. Construction Process.
During the construction process, the prospective
user will direct all questions to the Capital Projects Coordinator and
will personally visit the project site only when accompanied by the
Capital Projects Coordinator, or his designee.
5. Completion of the Project.
Upon completion of the project, the Capital Projects
Coordinator and the Office of State Construction will inspect the project
for compliance with the plans and specifications. The project will be turned
over to the user after this final inspection and formal acceptance of the
project by the Board of Trustees.
6. Equipment Acquisition.
b. Selection of Movable Equipment. It is the responsibility of the prospective user to choose suitable furnishings and other movable equipment, which will be purchased through the normal university purchasing procedures. It is important that the user expedite this phase because the procurement process on movable equipment quite frequently can take six or more months.
c. Movable Equipment List. University Purchasing Services will work with the user department to develop a Movable Equipment List for the Capital Improvement Project. It is not the intent of a capital improvement appropriation to fund a new program but rather to provide a facility to house an existing program. Therefore, the Movable Equipment List should include only such equipment as necessary to make the facility functional. The total cost of the items on this list, including tax, must not exceed the allotted amount. Purchasing Services will submit the Movable Equipment List to the Capital Projects Coordinator.
d. Requisitioning of Equipment.
All movable equipment must be approved for purchase by UNC-General Administration.
The Capital Projects Coordinator will notify the user when approval is
gained or if there are any exceptions. The user will then prepare a Requisition
Input/Authorization Form (see PUR 1.10) and forward
the completed input form to the Capital Projects Coordinator. The requisition
will be transmitted to Purchasing through the Capital Projects Coordinator.
8. Moving.
The Capital Projects Coordinator will advise
the user of the date scheduled for moving in or out of a building. Upon
notification, the user should follow standard UNCW moving procedures outlined
in Procedure AUX 9.40. If additional assistance
is needed, the user may contact the Moving Services Supervisor (extension
3620).
9. Problems.
The user of the facility will report any shortcomings,
deficiencies, or malfunctions in the facility to the Work Order Desk at
the Physical Plant (extension 3101).
10. General Assistance.
The Capital Projects Coordinator will be available
to provide assistance during any part of the Capital Improvement process,
including the period following occupancy.