Architects: Corley Redfoot Zack, BMS Architects, Wilmington
| Phase of Work | Architects | Time | Submittal Dates |
| Program & Schematic Design State Construction Office/Dept. of Insurance(DOI) Design Development SCO/DOI Approval Construction Documents SCO/DOI Approval Bid Process Ground Breaking Construction Admin. Post Construction Tentative Opening Date Grand Opening Celebration |
Zack/BMS Zack/BMS Zack/BMS ---------- BMS ---------- BMS/Zack ---------- BMS/Zack BMS |
8 weeks 7 weeks 12 weeks 8 weeks 24 weeks 8 weeks 4-6 weeks estimated 18 mths 4 weeks |
9/27/96 ---------- 2/28/97 ---------- 1/9/98 ---------- Bid Opening - June 25, 1998 5/1/98 - Ceremonial Actual - Sept. '98 3/00 ---------- 4/1/00
|