Architects: Corley Redfoot Zack, BMS Architects, Wilmington

Phase of Work Architects Time Submittal Dates
Program &
Schematic Design

State Construction
Office/Dept. of
Insurance(DOI)

Design
Development

SCO/DOI
Approval

Construction
Documents

SCO/DOI
Approval

Bid
Process


Ground
Breaking


Construction
Admin.

Post Construction

Tentative Opening Date

Grand Opening Celebration

Zack/BMS


Zack/BMS



Zack/BMS


----------


BMS


----------


BMS/Zack



----------



BMS/Zack


BMS
8 weeks


7 weeks



12 weeks


8 weeks


24 weeks


8 weeks


4-6 weeks



estimated



18 mths

4 weeks
9/27/96


----------



2/28/97


----------


1/9/98


----------


Bid Opening - June 25, 1998


5/1/98 - Ceremonial
Actual - Sept. '98

3/00

----------

4/1/00


4/11/00

 