Aerial View of Chancellor's Walk |
Description: |
Storm Drainage, Sidewalk Upgrades, Lighting, Signage, Seating,Recycling/Trash and Landscaping Upgrades. |
UNCW Project Manager: |
James Ross 910-962-7455 rossj@uncw.edu |
Architect: |
Sears Design Group |
Contractor: |
Skinner Smith - for Drainage and Concrete Thomson & Company - for Brick Paving Lancaster Electric - for Electrical |
Current Status: |
Drainage, pavers and walkway repair are complete. Remaining irrigation is in progress. The crossing of Reynolds Drive will be repaved after the Energy Plant Pipeline is completed. |
Estimated Completion Date: |
Estimated Completion Date - 2009 |
| Revised: 9/23/09 |