Central Energy Plant - to provide HVAC to School of Nursing building. |
| Description: | Pre-Fab building housing Central Energy Plant. Pipelines to provide HVAC to Nursing building and Wagoner Hall. Future connections for Teaching Lab, Allied Health and others in the area. |
UNCW Project Manager: |
Steve Sharpe 910-962-7454 sharpes@uncw.edu |
| Architect: | Norris, Kuske & Tunstall |
| Contractor: | Hale Building - Pre-fab building Thomson & Company - New Parking Entrance |
| Current Status: | Construction of the building structure Phase I is complete. Phase II is under construction with interior piping underway. Boilers and cooling towers are in place. Underground piping to Nursing Building will start in October, 2009.. |
Estimated Completion Date: |
Summer 2010 |
| Revised: 9/23/09 |